Generate a Cashflow Forecast
Create a monthly cashflow forecast with cumulative expenditure profile and S-curve data for construction project financial planning.
IntermediateCommercial ManagerBudget Forecasting
Overview
This workflow turns a programme and a contract sum into a monthly cashflow forecast: expenditure profile, valuation income, retention, and the net cash position month by month, with an S-curve shape that reflects how the job actually builds.
The output is the thing your finance director, your funder and your monthly report all want, and it is the thing most people build by hand in a spreadsheet every month.
The point of a cashflow forecast is not the total. You already know the total, it is the contract sum. The point is the trough: the month where you are furthest out of pocket, and how much funding you need to get through it. Everything else in the forecast is scaffolding around that one number.
WHEN TO USE THIS
Use it at contract award, when you need a first cashflow for the funder or the board and you have a programme but no history.
Use it monthly, to reforecast. This is where it earns its keep. The programme has moved, variations have landed, and the profile you drew in month one is now fiction. Rerunning it with current numbers takes minutes.
Use it when you are testing a scenario. What does a six-week delay to the frame do to the funding requirement? What if the client's payment terms go from 14 to 30 days? Change one input and look at the trough.
Use it on any job where the funding is tight enough that the trough matters, which in UK contracting is most of them.
WHEN NOT TO USE THIS
Do not use it as your actual cost control. A cashflow forecast is a funding tool. It is not a cost report and it is not a CVR. It tells you when money moves, not whether you are making any. If your margin is wrong, this forecast will show you a beautifully profiled route to losing it on schedule.
Do not use AI-generated profiles where you have real data. If you are in month nine of fifteen, your actual valuations to date beat any modelled S-curve. Use the actuals for the months that have happened and only model the remainder. People forget this and re-model the whole job every month, which throws away the best information they have.
Do not use it for a genuinely front-loaded or lumpy job without saying so. A scheme that is 60 percent one M&E package delivered in two deliveries does not have an S-curve, it has a staircase. The prompt has a front-end loading field for a reason. Fill it in honestly.
Do not hand the raw output to a funder. It is a first draft with modelled numbers in it. Your name goes on the version that goes out, and you should be able to defend every line.
COMMON MISTAKES
Confusing expenditure with valuation. They are different curves and the gap between them is your problem. Your costs go out when the subbies invoice. Your money comes in after the valuation, after the payment notice, after the payment period. On a monthly valuation with 14-day terms, that is a lag of roughly six weeks between spending and being paid, and if the model does not have that lag in it, the trough will look far shallower than it is.
Forgetting retention actually gets held. 3 percent sounds small until you see it as a line on a £14m job. Half of it usually stays put until practical completion and the rest until the end of the defects period, which is often well past the end of your forecast. Model it as held cash, not as a footnote.
Trusting the AI's arithmetic. This is the one that catches people. AI models are not calculators. Ask for fifteen months of expenditure that sums to £14.2m and it will produce a table that looks completely right and adds up to £14.34m. Check the totals. Every time. If the cumulative column does not land exactly on the contract sum, the whole forecast is wrong and it is wrong in a way that looks fine.
FREQUENTLY ASKED QUESTIONS
What is an S-curve and why does construction spend follow one?
The cumulative expenditure curve on most construction projects is S-shaped: slow at the start, steep in the middle, flattening at the end. It happens because of how jobs mobilise. Early on you have a small gang doing enabling and substructure. In the middle you have the frame, envelope and M&E rough-in all running at once with maximum labour on site. At the end you are down to snagging and commissioning with a handful of people. Draw cumulative spend against time and you get an S. If your forecast is a straight line, it is not a forecast, it is a division sum.
How accurate is an AI-generated cashflow?
The shape is usually reasonable. The numbers are as good as your inputs and the arithmetic needs checking. Treat it as a well-informed first draft that saves you an hour of spreadsheet work, not as an output you can issue. The one thing it genuinely cannot know is your job: that the steel is on a six-week lead and lands in one payment, or that the client always pays on day 29.
Should the forecast be based on cost or on value?
Both, and that is the entire point of the exercise. Model expenditure (what you pay out) and valuation income (what you get in) as separate lines, then the net position is the difference. A forecast with only one of them tells you nothing about funding. If you are only being asked for one, ask which question they are actually trying to answer.
How does retention affect the cashflow?
It withholds a percentage of every valuation, commonly 3 to 5 percent on UK contracts, usually with half released at practical completion and the balance at the end of the defects liability period. On a £14m job at 3 percent that is £426,000 sitting with the client, and the second half of it typically falls outside a 15-month forecast entirely. Model it explicitly as a held line, because it is real money and it is the difference between the forecast and the bank.
What payment terms should I model?
Whatever your contract says, not what you hope. Under the Housing Grants, Construction and Regeneration Act 1996 as amended, the contract sets the due date and the final date for payment, and the payment notice and pay less notice regime hangs off those. Read the dates out of your contract and model those. And model your subcontract payment terms separately, because the gap between when you pay them and when you get paid is exactly what the forecast is measuring.
Want all 50 prompts in one downloadable pack?
The Construction AI Prompt Pack includes every workflow prompt, 13 editable templates, and role-specific cheat sheets.
Get the Pack - £29
Instant download
Prompt
You are a Commercial Manager preparing a cashflow forecast for a UK construction project. Generate a monthly cashflow forecast based on the following: Project Details: - Project: [PROJECT NAME] - Contract Value (including approved variations): [VALUE, e.g., £14,200,000] - Start on Site Date: [DATE, e.g., January 2025] - Planned Completion Date: [DATE, e.g., March 2026] - Contract Duration: [MONTHS, e.g., 15 months] - Current Month: [MONTH, e.g., Month 5 of 15] - Retention Percentage: [%, e.g., 3%] - Payment Terms: [TERMS, e.g., Monthly valuations, 14 days for payment] - Front-End Loading: [YES/NO and brief note, e.g., Yes — significant substructure and steel package in first 4 months] Expenditure Profile Characteristics: - Early Works (Months 1-3): [DESCRIPTION, e.g., Enabling works, piling, substructure — moderate spend] - Peak Construction (Months 4-10): [DESCRIPTION, e.g., Frame, envelope, and M&E rough-in — high spend period] - Fit-Out & Commissioning (Months 11-15): [DESCRIPTION, e.g., Fit-out, commissioning, external works — declining spend] Generate: 1. Monthly Cashflow Table with columns: - Month Number and Calendar Month - Monthly Expenditure (cost) - Cumulative Expenditure - Monthly Valuation (income) - Cumulative Valuation - Retention Held - Net Cash Position 2. Cashflow Summary showing: - Total forecast expenditure vs contract value - Peak monthly expenditure month and amount - Maximum cash funding requirement and the month it occurs - Forecast margin and margin percentage 3. S-Curve Description — describe the shape of the cumulative expenditure curve in text (since we cannot draw a graph), noting the inflection points and the months of peak activity 4. Key Assumptions and Risks to the cashflow forecast Ensure the expenditure profile follows a realistic S-curve pattern for a UK construction project of this type.
Example Output
WORKED EXAMPLE: £4.2M PRIMARY SCHOOL EXTENSION A real shape of job. Two-storey teaching block extension to an occupied primary school in Taunton, JCT Design and Build 2016, 11 months, works confined to term time restrictions with the noisy demolition in the summer holidays. ── WHAT GOES IN ── Project: Bishops Hull Primary, Teaching Block Extension Contract Value (incl. approved variations): £4,240,000 Start on Site: 1 September 2026 Planned Completion: 31 July 2027 Duration: 11 months Current Month: Month 1 of 11 Retention: 3%, half released at PC, balance at end of 12-month DLP Payment Terms: Monthly valuations, due date 7 days after valuation, final date for payment 21 days after due date Front-End Loading: Yes. Demolition and substructure compressed into months 1-2 to use the summer holiday window. Steel frame ordered month 1, six-week lead, delivered and paid in month 3. Expenditure profile: - Months 1-2: demolition, enabling, piling, substructure. Heavy early spend due to holiday window. - Months 3-7: steel frame, envelope, roof, M&E first fix. Peak. - Months 8-11: fit-out, commissioning, external works, handover. Declining. ── WHAT COMES OUT ── MONTHLY CASHFLOW FORECAST | Mth | Month | Expenditure | Cum. Exp | Valuation | Cum. Val | Retention held | Cash received | Net cash position | |-----|-------|------------|----------|-----------|----------|---------------|---------------|-------------------| | 1 | Sep 26 | £310,000 | £310,000 | £330,000 | £330,000 | £9,900 | £0 | -£310,000 | | 2 | Oct 26 | £395,000 | £705,000 | £420,000 | £750,000 | £22,500 | £320,100 | -£384,900 | | 3 | Nov 26 | £540,000 | £1,245,000 | £575,000 | £1,325,000 | £39,750 | £407,400 | -£517,500 | | 4 | Dec 26 | £480,000 | £1,725,000 | £510,000 | £1,835,000 | £55,050 | £557,750 | -£439,750 | | 5 | Jan 27 | £515,000 | £2,240,000 | £545,000 | £2,380,000 | £71,400 | £494,700 | -£460,050 | | 6 | Feb 27 | £495,000 | £2,735,000 | £525,000 | £2,905,000 | £87,150 | £528,650 | -£426,400 | | 7 | Mar 27 | £450,000 | £3,185,000 | £480,000 | £3,385,000 | £101,550 | £509,250 | -£367,150 | | 8 | Apr 27 | £385,000 | £3,570,000 | £410,000 | £3,795,000 | £113,850 | £465,600 | -£286,550 | | 9 | May 27 | £310,000 | £3,880,000 | £330,000 | £4,125,000 | £123,750 | £397,700 | -£198,850 | | 10 | Jun 27 | £185,000 | £4,065,000 | £75,000 | £4,200,000 | £126,000 | £320,100 | -£63,750 | | 11 | Jul 27 | £110,000 | £4,175,000 | £40,000 | £4,240,000 | £127,200 | £72,750 | -£101,000 | Note: valuation income is shown received in the month it is paid, roughly one month after the valuation, reflecting the 7-day due date and 21-day final date for payment. Month 1's valuation is received in month 2. This lag is the whole reason the net position stays negative throughout. CASHFLOW SUMMARY Total forecast expenditure: £4,175,000 Contract value: £4,240,000 Forecast margin: £65,000 (1.5%) Peak monthly expenditure: Month 3 (Nov 26), £540,000 Maximum cash funding requirement: £517,500, occurring in Month 3 (Nov 26) Retention held at PC: £127,200. £63,600 released at PC (Jul 27), £63,600 at end of DLP (Jul 28, outside this forecast) S-CURVE DESCRIPTION The cumulative expenditure curve is a compressed S with an early shoulder. It rises steeply from month 1 rather than easing in, because the demolition and substructure are forced into the summer holiday window and the steel is paid in month 3 on a six-week lead. The first inflection is at month 3, where the curve reaches 30 percent of total spend by month 3 of 11, which is well ahead of a standard profile. It then runs close to linear through the peak from months 3 to 7, and flattens from month 8 as fit-out gives way to commissioning. By month 9 the job is 93 percent spent with two months to run. The consequence of that early shoulder is the trough. Maximum funding requirement of £517,500 lands in month 3 rather than the middle of the job, and it is driven by the steel payment landing before the first two valuations have been paid. KEY ASSUMPTIONS AND RISKS 1. Steel payment of approximately £310,000 assumed in month 3 on delivery. If the fabricator wants payment on order, the trough moves to month 2 and deepens by roughly £150,000. 2. Client pays to contractual terms. Every week of late payment moves the trough by roughly £120,000 on this profile. 3. Margin of 1.5 percent is thin. This forecast has no headroom for a delay. A four-week overrun into the September term would add prelims against no additional income and turn the margin negative. 4. Retention released in full at PC assumed on time. Second half falls outside the forecast entirely. 5. No allowance for the risk that term-time noise restrictions push demolition beyond the holiday window. That is the single biggest programme risk on this job and it sits directly on the front-loaded section of the curve. ── THE BIT THAT MATTERS ── Look at the maximum funding requirement: £517,500 in month 3 on a £4.24m job. That is 12 percent of contract value that you have to find, in month 3, on a scheme with a £65,000 margin. That is the number you take to the board. Everything else in the table is working out. And check the arithmetic before you send it. The classic failure on a table like this is a cumulative column that drifts a few thousand off the stated total: everything looks immaculate, every row is plausible, and the totals do not tie. The model does not add up, it predicts what an addition looks like. Sum the column yourself, every time.
Use Case
Use at contract award to build the first cashflow, then monthly to reforecast as the programme moves and variations land.
Input the contract value, the dates, the retention and payment terms, and a short description of how the spend actually profiles, and you get a monthly table with expenditure, valuation income, retention held and the net cash position, plus the funding trough and an S-curve description.
Also useful for scenario testing before a commercial meeting. Change the payment terms or push a key package back six weeks and see what happens to the funding requirement.
One rule: once the job is running, feed in your actual valuations for the months that have happened and only model the remainder. Real data beats a modelled curve every time.
All 50 Prompts
Get every prompt in one pack
Stop copy-pasting one prompt at a time. The Construction AI Prompt Pack includes all 50 workflows as editable documents, organised by role, ready to use offline.
£29one-time
Get the Prompt PackInstant download. Editable files.
Try our software
Want these prompts pre-built?
AI Construction Copilot has all these workflows ready to run — no copy-pasting needed. Built specifically for construction professionals.
Try FreeFree newsletter
Get AI Tips Weekly
New construction AI workflows, prompts, and templates delivered to your inbox every week.
Subscribe FreeNo spam. Unsubscribe anytime.