Generate a Cashflow Forecast
Create a monthly cashflow forecast with cumulative expenditure profile and S-curve data for construction project financial planning.
Editor: Owen HaggerLast updated
Overview
Want more templates like this?
Get new AI workflows and construction templates delivered weekly. Free.
No spam ever.
Prompt
You are a Commercial Manager preparing a cashflow forecast for a UK construction project. Generate a monthly cashflow forecast based on the following: Project Details: - Project: [PROJECT NAME] - Contract Value (including approved variations): [VALUE, e.g., £14,200,000] - Start on Site Date: [DATE, e.g., January 2025] - Planned Completion Date: [DATE, e.g., March 2026] - Contract Duration: [MONTHS, e.g., 15 months] - Current Month: [MONTH, e.g., Month 5 of 15] - Retention Percentage: [%, e.g., 3%] - Payment Terms: [TERMS, e.g., Monthly valuations, 14 days for payment] - Front-End Loading: [YES/NO and brief note, e.g., Yes, significant substructure and steel package in first 4 months] Expenditure Profile Characteristics: - Early Works (Months 1-3): [DESCRIPTION, e.g., Enabling works, piling, substructure, moderate spend] - Peak Construction (Months 4-10): [DESCRIPTION, e.g., Frame, envelope, and M&E rough-in, high spend period] - Fit-Out & Commissioning (Months 11-15): [DESCRIPTION, e.g., Fit-out, commissioning, external works, declining spend] Generate: 1. Monthly Cashflow Table with columns: - Month Number and Calendar Month - Monthly Expenditure (cost) - Cumulative Expenditure - Monthly Valuation (income) - Cumulative Valuation - Retention Held - Net Cash Position 2. Cashflow Summary showing: - Total forecast expenditure vs contract value - Peak monthly expenditure month and amount - Maximum cash funding requirement and the month it occurs - Forecast margin and margin percentage 3. S-Curve Description: describe the shape of the cumulative expenditure curve in text (since we cannot draw a graph), noting the inflection points and the months of peak activity 4. Key Assumptions and Risks to the cashflow forecast Ensure the expenditure profile follows a realistic S-curve pattern for a UK construction project of this type.
Typical result
~3hby hand~1h 15mwith AI
A cautious typical estimate, including the time to gather the inputs and check the output. It varies with the job.
What it replaces: Building the monthly cash flow forecast by hand.
What you still check
- Values and timings follow the programme and payment terms
- Retention and payment periods are modelled correctly
- The calculation sits in a spreadsheet you can check, not in a chat reply
See how much of your money a job ties up with the cash tied up calculator on constructionrating.co.uk.
Example Output
WORKED EXAMPLE: £4.2M PRIMARY SCHOOL EXTENSION A real shape of job. Two-storey teaching block extension to an occupied primary school in Taunton, JCT Design and Build 2016, 11 months, works confined to term time restrictions with the noisy demolition in the summer holidays. ── WHAT GOES IN ── Project: Bishops Hull Primary, Teaching Block Extension Contract Value (incl. approved variations): £4,240,000 Start on Site: 1 September 2026 Planned Completion: 31 July 2027 Duration: 11 months Current Month: Month 1 of 11 Retention: 3%, half released at PC, balance at end of 12-month DLP Payment Terms: Monthly valuations, due date 7 days after valuation, final date for payment 21 days after due date Front-End Loading: Yes. Demolition and substructure compressed into months 1-2 to use the summer holiday window. Steel frame ordered month 1, six-week lead, delivered and paid in month 3. Expenditure profile: - Months 1-2: demolition, enabling, piling, substructure. Heavy early spend due to holiday window. - Months 3-7: steel frame, envelope, roof, M&E first fix. Peak. - Months 8-11: fit-out, commissioning, external works, handover. Declining. ── WHAT COMES OUT ── MONTHLY CASHFLOW FORECAST | Mth | Month | Expenditure | Cum. Exp | Valuation | Cum. Val | Retention held | Cash received | Net cash position | |-----|-------|------------|----------|-----------|----------|---------------|---------------|-------------------| | 1 | Sep 26 | £310,000 | £310,000 | £330,000 | £330,000 | £9,900 | £0 | -£310,000 | | 2 | Oct 26 | £395,000 | £705,000 | £420,000 | £750,000 | £22,500 | £320,100 | -£384,900 | | 3 | Nov 26 | £540,000 | £1,245,000 | £575,000 | £1,325,000 | £39,750 | £407,400 | -£517,500 | | 4 | Dec 26 | £480,000 | £1,725,000 | £510,000 | £1,835,000 | £55,050 | £557,750 | -£439,750 | | 5 | Jan 27 | £515,000 | £2,240,000 | £545,000 | £2,380,000 | £71,400 | £494,700 | -£460,050 | | 6 | Feb 27 | £495,000 | £2,735,000 | £525,000 | £2,905,000 | £87,150 | £528,650 | -£426,400 | | 7 | Mar 27 | £450,000 | £3,185,000 | £480,000 | £3,385,000 | £101,550 | £509,250 | -£367,150 | | 8 | Apr 27 | £385,000 | £3,570,000 | £410,000 | £3,795,000 | £113,850 | £465,600 | -£286,550 | | 9 | May 27 | £310,000 | £3,880,000 | £330,000 | £4,125,000 | £123,750 | £397,700 | -£198,850 | | 10 | Jun 27 | £185,000 | £4,065,000 | £75,000 | £4,200,000 | £126,000 | £320,100 | -£63,750 | | 11 | Jul 27 | £110,000 | £4,175,000 | £40,000 | £4,240,000 | £127,200 | £72,750 | -£101,000 | Note: valuation income is shown received in the month it is paid, roughly one month after the valuation, reflecting the 7-day due date and 21-day final date for payment. Month 1's valuation is received in month 2. This lag is the whole reason the net position stays negative throughout. CASHFLOW SUMMARY Total forecast expenditure: £4,175,000 Contract value: £4,240,000 Forecast margin: £65,000 (1.5%) Peak monthly expenditure: Month 3 (Nov 26), £540,000 Maximum cash funding requirement: £517,500, occurring in Month 3 (Nov 26) Retention held at PC: £127,200. £63,600 released at PC (Jul 27), £63,600 at end of DLP (Jul 28, outside this forecast) S-CURVE DESCRIPTION The cumulative expenditure curve is a compressed S with an early shoulder. It rises steeply from month 1 rather than easing in, because the demolition and substructure are forced into the summer holiday window and the steel is paid in month 3 on a six-week lead. The first inflection is at month 3, where the curve reaches 30 percent of total spend by month 3 of 11, which is well ahead of a standard profile. It then runs close to linear through the peak from months 3 to 7, and flattens from month 8 as fit-out gives way to commissioning. By month 9 the job is 93 percent spent with two months to run. The consequence of that early shoulder is the trough. Maximum funding requirement of £517,500 lands in month 3 rather than the middle of the job, and it is driven by the steel payment landing before the first two valuations have been paid. KEY ASSUMPTIONS AND RISKS 1. Steel payment of approximately £310,000 assumed in month 3 on delivery. If the fabricator wants payment on order, the trough moves to month 2 and deepens by roughly £150,000. 2. Client pays to contractual terms. Every week of late payment moves the trough by roughly £120,000 on this profile. 3. Margin of 1.5 percent is thin. This forecast has no headroom for a delay. A four-week overrun into the September term would add prelims against no additional income and turn the margin negative. 4. Retention released in full at PC assumed on time. Second half falls outside the forecast entirely. 5. No allowance for the risk that term-time noise restrictions push demolition beyond the holiday window. That is the single biggest programme risk on this job and it sits directly on the front-loaded section of the curve. ── THE BIT THAT MATTERS ── Look at the maximum funding requirement: £517,500 in month 3 on a £4.24m job. That is 12 percent of contract value that you have to find, in month 3, on a scheme with a £65,000 margin. That is the number you take to the board. Everything else in the table is working out. And check the arithmetic before you send it. The classic failure on a table like this is a cumulative column that drifts a few thousand off the stated total: everything looks immaculate, every row is plausible, and the totals do not tie. The model does not add up, it predicts what an addition looks like. Sum the column yourself, every time.
Use Case
When not to use it
Don't treat a chat reply as your cash flow model. Use the workflow to organise the inputs and explain the shape of the forecast, then keep the calculation in a spreadsheet where every figure can be checked.
It's also not a substitute for the business's own cash forecast across all jobs, which needs real bank, payroll and overhead figures.
Common mistakes
- Spreading value evenly across the programme instead of following the actual sequence of work.
- Ignoring payment terms: the gap between doing the work, the application, the payment notice and the money arriving.
- Forgetting retention, both what's held from you and what you hold from subcontractors.
- Leaving out large one-off costs such as plant purchases, bonds or materials paid up front.
- Not updating the forecast when the programme changes.
Frequently asked questions
- What is an S-curve in construction?
- A chart of cumulative cost or value against time. It's usually shaped like an S because spending starts slowly, speeds up through the main works and slows towards completion.
- Can AI build the forecast for me?
- It can turn your programme, values and payment terms into a structured monthly profile and explain it. Keep the numbers in a spreadsheet you control and check them.
- How do payment terms change the forecast?
- They shift when money comes in. A month of work might not be paid until weeks later, so the cash position lags the value earned.
- How often should I update it?
- At least monthly, alongside the valuation and the CVR, and whenever the programme changes significantly.
Get AI Tips Weekly
New construction AI workflows, prompts, and templates delivered to your inbox every week.
Subscribe FreeNo spam. Unsubscribe anytime.