Generate a Preliminary Cost Plan

Quickly generate a structured elemental cost plan for early-stage construction projects using AI.

IntermediateQuantity SurveyorCost Estimation

Overview

This workflow helps Quantity Surveyors create preliminary cost plans at RIBA Stage 2-3. It generates an elemental breakdown using standard categories, allowing you to quickly produce a first draft cost plan that can then be refined with project-specific rates and quantities.

Want all 50 prompts in one downloadable pack?

The Construction AI Prompt Pack includes every workflow prompt, 13 editable templates, and role-specific cheat sheets.

Get the Pack - £29

Instant download

Prompt

You are an experienced UK Quantity Surveyor. Generate a preliminary elemental cost plan for the following project:

Project: [PROJECT TYPE, e.g., New-build secondary school]
Location: [LOCATION, e.g., Greater Manchester]
Gross Internal Floor Area: [GIFA, e.g., 8,500 sqm]
Storeys: [NUMBER, e.g., 3]
Construction Start: [DATE, e.g., Q2 2025]
Budget Envelope: [BUDGET, e.g., £18M]

Present the cost plan as a table with columns:
- Element (using NRM1 categories)
- £/sqm Rate
- Total Cost
- % of Total

Include: Facilitating Works, Substructure, Superstructure, Internal Finishes, Fittings & Furnishings, Services, External Works, Preliminaries, Overheads & Profit, and a Contingency allowance.

Add brief notes explaining key assumptions and exclusions.

Example Output

PRELIMINARY COST PLAN — New-Build Secondary School
Location: Greater Manchester | GIFA: 8,500 sqm | 3 Storeys

| Element                      | £/sqm  | Total        | % of Total |
|------------------------------|--------|--------------|------------|
| 0 Facilitating Works         | £35    | £297,500     | 1.7%       |
| 1 Substructure               | £145   | £1,232,500   | 7.0%       |
| 2 Superstructure             | £485   | £4,122,500   | 23.4%      |
| 3 Internal Finishes          | £165   | £1,402,500   | 8.0%       |
| 4 Fittings & Furnishings     | £95    | £807,500     | 4.6%       |
| 5 Services                   | £420   | £3,570,000   | 20.3%      |
| 6 External Works             | £110   | £935,000     | 5.3%       |
| 7 Preliminaries (14%)        | £204   | £1,731,300   | 9.8%       |
| 8 OH&P (6%)                  | £99    | £845,850     | 4.8%       |
| 9 Design Risk Contingency    | £105   | £892,500     | 5.1%       |
| 10 Construction Contingency  | £105   | £892,500     | 5.1%       |
| TOTAL                        | £1,968 | £16,730,150  | 95.2%      |

Assumptions:
- Rates based on BCIS median for secondary schools in NW England, Q1 2025
- Excludes: VAT, professional fees, land costs, Section 106 contributions
- Includes for enhanced acoustic and ventilation requirements

Use Case

Use this at RIBA Stage 2 or Stage 3 when you need to produce a quick cost plan for client budget discussions. Replace the placeholder values with your actual project details.

Recommended Tool

ChatGPT
OpenAI's conversational AI assistant. Ideal for drafting reports, analysing data, and generating construction documentat...
AI AssistantFree / Plus $20/mo
Learn more →

Related Guide

AI for Cost Estimation: A Complete Guide
How to use AI tools to speed up cost estimation, from preliminary budgets to detailed BOQs. Practical workflows for QS a...
Intermediate12 min read
All 50 Prompts

Get every prompt in one pack

Stop copy-pasting one prompt at a time. The Construction AI Prompt Pack includes all 50 workflows as editable documents, organised by role, ready to use offline.

£29one-time
Get the Prompt Pack

Instant download. Editable files.

Try our software

Want these prompts pre-built?

AI Construction Copilot has all these workflows ready to run — no copy-pasting needed. Built specifically for construction professionals.