Generate a Preliminary Cost Plan

Quickly generate a structured elemental cost plan for early-stage construction projects using AI.

Editor: Owen HaggerLast updated

Overview

This workflow helps Quantity Surveyors create preliminary cost plans at RIBA Stage 2-3. It generates an elemental breakdown using standard categories, allowing you to quickly produce a first draft cost plan that can then be refined with project-specific rates and quantities.

Want more templates like this?

Get new AI workflows and construction templates delivered weekly. Free.

Subscribe Free

No spam ever.

Prompt

You are an experienced UK Quantity Surveyor. Generate a preliminary elemental cost plan for the following project:

Project: [PROJECT TYPE, e.g., New-build secondary school]
Location: [LOCATION, e.g., Greater Manchester]
Gross Internal Floor Area: [GIFA, e.g., 8,500 sqm]
Storeys: [NUMBER, e.g., 3]
Construction Start: [DATE, e.g., Q2 2025]
Budget Envelope: [BUDGET, e.g., £18M]

Present the cost plan as a table with columns:
- Element (using NRM1 categories)
- £/sqm Rate
- Total Cost
- % of Total

Include: Facilitating Works, Substructure, Superstructure, Internal Finishes, Fittings & Furnishings, Services, External Works, Preliminaries, Overheads & Profit, and a Contingency allowance.

Add brief notes explaining key assumptions and exclusions.

Typical result

~8hby hand~3hwith AI

A cautious typical estimate, including the time to gather the inputs and check the output. It varies with the job.

What it replaces: Building an early cost plan by hand from benchmarks.

What you still check

  • Rates come from your own cost data, not AI guesses
  • Quantities and gross internal floor area are right
  • Assumptions and exclusions are written down

Example Output

PRELIMINARY COST PLAN: New-Build Secondary School
Location: Greater Manchester | GIFA: 8,500 sqm | 3 Storeys

| Element                      | £/sqm  | Total        | % of Total |
|------------------------------|--------|--------------|------------|
| 0 Facilitating Works         | £35    | £297,500     | 1.7%       |
| 1 Substructure               | £145   | £1,232,500   | 7.0%       |
| 2 Superstructure             | £485   | £4,122,500   | 23.4%      |
| 3 Internal Finishes          | £165   | £1,402,500   | 8.0%       |
| 4 Fittings & Furnishings     | £95    | £807,500     | 4.6%       |
| 5 Services                   | £420   | £3,570,000   | 20.3%      |
| 6 External Works             | £110   | £935,000     | 5.3%       |
| 7 Preliminaries (14%)        | £204   | £1,731,300   | 9.8%       |
| 8 OH&P (6%)                  | £99    | £845,850     | 4.8%       |
| 9 Design Risk Contingency    | £105   | £892,500     | 5.1%       |
| 10 Construction Contingency  | £105   | £892,500     | 5.1%       |
| TOTAL                        | £1,968 | £16,730,150  | 95.2%      |

Assumptions:
- Rates based on BCIS median for secondary schools in NW England, Q1 2025
- Excludes: VAT, professional fees, land costs, Section 106 contributions
- Includes for enhanced acoustic and ventilation requirements

Use Case

Use this at RIBA Stage 2 or Stage 3 when you need to produce a quick cost plan for client budget discussions. Replace the placeholder values with your actual project details.

Recommended Tool

ChatGPT
OpenAI's conversational AI assistant. Ideal for drafting reports, analysing data, and generating construction documentat...
AI AssistantFree plan; paid Plus and business plans
Learn more →

Related Guide

AI Construction Estimating: How It Works, What It Gets Wrong, and a UK Worked Example
AI construction estimating uses AI tools to speed up quantity take-off, pricing, scope checks, and tender adjudication....
Intermediate12 min read
Free newsletter

Get AI Tips Weekly

New construction AI workflows, prompts, and templates delivered to your inbox every week.

Subscribe Free

No spam. Unsubscribe anytime.

More AI workflows for Quantity Surveyors

All Quantity Surveyor workflows →

Related resources